Construction Log August 2015
Construction of Sacramento State’s new stormwater management devices began on Monday, July 6, 2015. As of mid-August, activities included utility locating; asphalt and turf removal; excavation; tree and streetlight relocation; concrete forming; and the placement of drain inlets, aggregate storage, and bioretention treatment soils.