Construction Log, December 7, 2015
The contractor will be returning to Calaveras Hall to clean up the disconnected downspouts, which are currently unpainted and have rough edges. The cleanup will include adding elbows to better direct... Read more about the progress on December 7, 2015
Construction Log, September 25, 2015
The bioretention planters in Lots 7 and 10 and rain gardens along College Town Drive are complete, including vegetative cover, however extreme heat took its toll on several plants... Read more about the progress on September 25, 2015
Construction Log, August 25, 2015
Construction of the bioretention planters and bioswales in Parking Lots 7 and 10 is complete, and the vegetation is being established... Read more about the progress on August 25, 2015
Construction Log, August 11, 2015
Construction of Sacramento State's new stormwater management devices began on Monday, July 6, 2015... Read more about the progress on August 11, 2015